A Message from the Wright County Highway Department:
Construction on the realignment of Braddock Avenue and a roundabout at County Highway 83 and County Highway 148 (Braddock Avenue) will begin on Monday, August 7.
The contractor will proceed with the construction in two stages:
Stage 1 – County Highway 83 will be closed just west of County Highway 148 (Braddock Avenue). Access to all government buildings will be via State Highway 25 to Co Highway 83 to County Highway 148 (Braddock Avenue).
Stage 2 – Construct the intersection of the realigned roadway to the existing County Highway 148 (Braddock Avenue) near the Highway Department entrance.
Access to the Public Works Building and Highway Department will be the same as Stage 1.
Access to the Government Center, Justice Center and Law Enforcement Center will be from the NORTH utilizing County Highway 113 and County Highway 148 (Braddock Avenue).
Stage 2 is anticipated to last approximately three weeks. Follow detour signs! The project is expected to be completed by Tuesday, September 26.
If you have any questions or would like additional information on this project, please contact: Chad Hausmann, Wright County Assistant Engineer chad.hausmann@co.wright.mn.us