County Highway (Hwy) 37, from Hwy 19 to Hwy 18, will be reconstructed beginning May 16th and is scheduled to be completed by October 15th, 2022. The project will include an overall detour that directs thru traffic to Hwy 18. Local residents will continue to have access on Hwy 37 for the duration of the reconstruction. Please pay attention to signage on the best way to access your property or get through the area. For updates during construction, please visit www.csah37.com
Below is a summary of the stages and approximate timeframes (weather-dependent):
• Stage 1: May 16th – August 5th
• Stage 2: August 8th – September 2nd
• Stage 3: September 6th – October 15th
Staging Map and Stage 1 Detour 