The Wright County Highway Department has provided a project update as of today (Sept. 11) on the CSAH 30 project in Delano.
Here are some of those updates:
• The contractor is completing the aggregate base work throughout the project.
• The contractor will begin electrical work and install the light fixtures near the McKinley Parkway intersection.
• The contractor could install curb late next week or early the following week at the McKinley Parkway intersection.
• The contractor will continue to work on shaping the ditches along CSAH 30, and bringing them to design grade.