Highway 18 Project - Construction Update

WC Logo - Color - Tiny

August 6, 2018 - CONSTRUCTION UPDATE: Work on County State Aid Highway (CSAH) 18 is approaching 40% complete as of August 3, 2018.  The Contractor continues to install storm sewer pipe and watermain pipe as well as removal of unsuitable soils under the roadway.  Additional areas of unsuitable soils were encountered along highway 18  that required extra work by the contractor.  It is anticipated that work will continue into the Fall of 2018, when traffic will be opened to the public, with completion of remaining work on the contract in 2019.

WSB & Associates is performing the inspection/construction management services for the work.  If you have construction related concerns during the project, please contact one of the following people:  Jeff Eggert, Project Manager, (612-360-1316); Kory Eichhorst, Project Inspector, (612-214-7741); Chad Hausmann, Assistant County Engineer, (763-682-7387); or Jeremy Carlson, Right-of-Way Agent, (763-682-7386).

Highway 18 Project Detour Map
Facebook Twitter Google Plus Email

Other News in Wright County News