The Wright Highway Department has provided an update on the progress of the CSAH 19 & 38 construction project in Albertville.
The project will be entering the next phase of Construction starting August 3. The following is a breakdown of proposed scheduling and Traffic Detour plans:
Mid-afternoon Monday, August 3, CSAH 19 from Lamplight Drive north to 70th Street will be closed. At that time, traffic from the I-94 ramp north to Lamplight will have access to all businesses along CSAH 19.
There will be a local business detour from Lamplight to 67th Street to provide access to Slumberland and Welcome Furniture.
A detour will be in place for approximately eight weeks.
This detour shall utilize County Road 37, MacIver Avenue and County Road 38 for northbound and southbound CSAH 19 traffic.